Tushar Mohanrao Khatavkar

Individual promoter · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date2 of 4 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tulip GreenP53000012333Kolhapur (M Corp.)2017Certificate Signed31 Dec 201831 Dec 2018On date
Tulip ClassicP53000015468Kolhapur (M Corp.)2018Certificate Signed31 Dec 201930 Jun 2024+54 months
Tulip ElementP53000026601Karvir2020Certificate Signed30 Dec 202231 Dec 2024+24 months
Tulip BloomP53000027941Kolhapur (M Corp.)2021Certificate Signed30 Jun 202330 Jun 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tulip GreenOn date
  • Tulip Classic+54 mo
  • Tulip Element+24 mo
  • Tulip BloomOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Tulip Classic (P53000015468).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology