Skip to content

Tulsi Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tulsi NandanP51600026346Nashik (M Corp.)2020Certificate Signed31 Jan 202431 Jan 2024On date
Tulsi VasundharaP51600051073Nashik (M Corp.)2023Certificate Signed1 Apr 20281 Aug 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tulsi NandanOn date
  • Tulsi Vasundhara+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Tulsi Vasundhara (P51600051073).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology