Tulip Properties
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Infinity Planet C And D WingP52100019792 | Pimpri Chinchawad (M Corp.) | 2019 | Certificate Signed | 31 Dec 2022 | 30 Dec 2024 | +24 months |
| Infinity Planet B WingP52100030463 | Moshi | 2021 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Infinity PlanetP52100034091 | Moshi | 2022 | Certificate Signed | 31 May 2026 | 31 May 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Infinity Planet C And D Wing (P52100019792).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology