Triumph Builders Llp

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mandlik Nagar Chs Ltd Phase II Rehab Wing E Pt And FP51800004077Borivali2017Not reported31 Dec 2018—On date
Triumph TowersP51800027364Borivali2020Certificate Signed30 Jun 202331 May 2024+11 months
Triumph SwastikP51800035067Borivali2022Certificate Signed30 Jun 202530 Jun 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mandlik Nagar Chs Ltd Phase II Rehab Wing E Pt And FOn date
  • Triumph Towers+11 mo
  • Triumph SwastikOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Triumph Towers (P51800027364).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology