Trimurti Developers
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Grand IconP52100006202 | Ambegaon Bk | 2017 | Certificate Signed | 31 May 2019 | 31 May 2019 | On date |
| SwapngandhP52100018059 | Kirkatwadi | 2018 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| WisteriaP52100046180 | Bavadhan Bk | 2022 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| The RiseP52100077093 | Dhayari (Part) | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Wisteria (P52100046180).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology