Tridhaatu Morya Developers Pvt Ltd
Company or firm · 1 project · 1 MahaRERA registration
Projects11 RERA registration
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tridhaatu MoryaP51800013775 | Kurla | 2017 | Not reported | 30 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Tridhaatu Morya (Suo Motu Case No. 15 of 2018) dated 6th March 2018 · Tridhaatu Morya · P51800013775 · 6 Mar 2018
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology