Tricity Realty Llp
Company or firm · 14 projects · 14 MahaRERA registrations
14Projects14 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date6 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tricity PalacioP51700002400 | Navi Mumbai (M Corp.) | 2017 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Tricity PanacheP51700003260 | Navi Mumbai (M Corp.) | 2017 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Tricity PromenadeP51700013737 | Navi Mumbai (M Corp.) | 2017 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Tricity LuxuriaP52000017110 | New Panvel | 2018 | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Tricity ErosP52000020294 | Kharghar | 2019 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Tricity MontviewP51700034413 | Navi Mumbai (M Corp.) | 2022 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Tricity waterfrontP52000048272 | Kalamboli | 2022 | Certificate Signed | 31 Dec 2027 | 31 Dec 2029 | +24 months |
| Tricity NatrajP51800050160 | Kurla | 2023 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Tricity BlissP52000052273 | Wahal | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Tricity CrestP52000054066 | New Panvel | 2023 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Tricity BayviewP52000054513 | Kalamboli | 2024 | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| Tricity AuraP52000055973 | Kalamboli | 2024 | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
| Tricity AspireP52000055992 | Kharghar | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Tricity HeritageP52000077294 | New Panvel | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Show all 14 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 14 registrations
Track record notes
- 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Tricity waterfront (P52000048272).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology