Town Developers
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+123 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Al MarjaanP51800003556 | Andheri | 2017 | Certificate Signed | 31 Dec 2018 | 31 Mar 2029 | +123 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 123 months, for Al Marjaan (P51800003556).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:AL MARJAAN (Regulatory Case No. 189 of 2024) dated 30 May 2024. · Al Marjaan · P51800003556 · 30 May 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology