Today Micron Developers
Company or firm · 1 project · 3 MahaRERA registrations
1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Utsav CityP52000016710 | Shivkar | 2018 | Certificate Signed | 30 Jun 2021 | 18 Sep 2023 | +27 months |
| Utsav CityP52000018102 | Shivkar | 2018 | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 months |
| Utsav CityP52000019069 | Shivkar | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 27 months, for Utsav City (P52000016710).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology