Today Micron Developers

Company or firm · 1 project · 3 MahaRERA registrations

1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Utsav CityP52000016710Shivkar2018Certificate Signed30 Jun 202118 Sep 2023+27 months
Utsav CityP52000018102Shivkar2018Certificate Signed30 Jun 202130 Dec 2022+18 months
Utsav CityP52000019069Shivkar2018Certificate Signed30 Dec 202230 Dec 2023+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Utsav City+27 mo
  • Utsav City+18 mo
  • Utsav City+12 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 27 months, for Utsav City (P52000016710).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology