The Squarefeet Company
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vijaya MauliP50500028545 | Pipla | 2021 | Certificate Signed | 21 Jun 2024 | 21 Jun 2024 | On date |
| Emzar HightownP50500049345 | Khasarmari | 2023 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Vijaya SaraswatiPP1190002501389 | Sondapar | 2025 | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- DeregisteredDeregistered: EMZAR HIGHTOWN · Emzar Hightown · P50500049345
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology