The Impressions

Company or firm · 5 projects · 5 MahaRERA registrations

Also appears as M/s The Impressions

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anant PrabhaP52000020612Khopoli2019Certificate Signed30 Mar 202330 Mar 2023On date
The HarmonyP51700046683Dombivli2022Certificate Signed31 Dec 202730 Apr 2028+4 months
MyraP51700056032Dombivli2024Certificate Signed31 Aug 202731 Dec 2027+4 months
Hanuman KutirP51700078332Kalyandombivali (M Corp.)2024Certificate Signed30 Apr 202730 Aug 2027+4 months
VedvikaPR1330002600676Dombivli2026Certificate Signed31 Dec 203130 Apr 2032+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anant PrabhaOn date
  • The Harmony+4 mo
  • Myra+4 mo
  • Hanuman Kutir+4 mo
  • Vedvika+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for The Harmony (P51700046683).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology