Company or firm · 6 projects · 7 MahaRERA registrations

6Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Excellaa ResidencyP52100021432Ambegaon Bk2019Certificate Signed30 Dec 202530 Dec 2025On date
Excellaa PlazzoP52100021440Ambegaon Bk2019Certificate Signed30 Dec 202530 Dec 2025On date
TremontP52100030433Mundhawa2021Certificate Signed31 Dec 202831 Dec 2028On date
PrimarcP52100047444Bavadhan Bk2022Certificate Signed31 Dec 202731 Dec 2027On date
VirtuP52100054268Pimple Nilakh2024Certificate Signed31 Dec 202630 Apr 2027+4 months
PolarisP52100080233Bavdhan Khurd2025Certificate Signed31 Dec 203031 Dec 2030On date
TremontP52100080608Mundhawa2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Excellaa ResidencyOn date
  • Excellaa PlazzoOn date
  • TremontOn date
  • PrimarcOn date
  • Virtu+4 mo
  • PolarisOn date
  • Tremont+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Virtu (P52100054268).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology