Tharwani Properties

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vedant Palacia Phase II Wing A2-PROTICAP51700032846Gandhare2022Not reported31 May 202230 Nov 2022+6 months
Vedant Palacia Phase III Wing A-AETIUSP51700033028Gandhare2022Certificate Signed30 Sep 202530 Sep 2025On date
Vedant Palacia Phase I Wing A1 PROPSERAP51700033038Gandhare2022Not reported31 May 202230 Nov 2022+6 months
Vedant Palacia Phase IV Wing B-BrutusP51700049317Gandhare2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Vedant Palacia Phase V Wing C-CassiusP51700054327Gandhare2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vedant Palacia Phase II Wing A2-PROTICA+6 mo
  • Vedant Palacia Phase III Wing A-AETIUSOn date
  • Vedant Palacia Phase I Wing A1 PROPSERA+6 mo
  • Vedant Palacia Phase IV Wing B-Brutus+4 mo
  • Vedant Palacia Phase V Wing C-CassiusOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 6 months, for Vedant Palacia Phase II Wing A2-PROTICA (P51700032846).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology