Tharwani Properties
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vedant Palacia Phase II Wing A2-PROTICAP51700032846 | Gandhare | 2022 | Not reported | 31 May 2022 | 30 Nov 2022 | +6 months |
| Vedant Palacia Phase III Wing A-AETIUSP51700033028 | Gandhare | 2022 | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| Vedant Palacia Phase I Wing A1 PROPSERAP51700033038 | Gandhare | 2022 | Not reported | 31 May 2022 | 30 Nov 2022 | +6 months |
| Vedant Palacia Phase IV Wing B-BrutusP51700049317 | Gandhare | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Vedant Palacia Phase V Wing C-CassiusP51700054327 | Gandhare | 2024 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 6 months, for Vedant Palacia Phase II Wing A2-PROTICA (P51700032846).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology