Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Thanekar PalacioP51700032795Badlapur (M Cl)2022Certificate Signed31 Dec 202431 Dec 2024On date
Thanekar Bkc ParamountPM1330002502099Belavli2026Not reported31 Dec 2028—On date
Thanekar Bkc VistaPR1330002502242Belavli2026Not reported31 May 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Thanekar PalacioOn date
  • Thanekar Bkc ParamountOn date
  • Thanekar Bkc VistaOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology