Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sarvoday Nagar Sector 1P51700007690Ambarnath(M Cl)2017Certificate Signed31 Jul 202531 Jul 2025On date
SaubhagyamP52000079995New Panvel2025Certificate Signed31 Dec 202830 Apr 2029+4 months
Sarvoday 1P51700081011Kalyan2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sarvoday Nagar Sector 1On date
  • Saubhagyam+4 mo
  • Sarvoday 1+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Saubhagyam (P52000079995).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology