Thalia And Gami Enterprises
Company or firm · 2 projects · 3 MahaRERA registrations
2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Gami AstersP51700025311 | Navi Mumbai (M Corp.) | 2020 | Not reported | 30 Dec 2024 | 31 Dec 2026 | +24 months |
| Gami EvaP51700031192 | Navi Mumbai (M Corp.) | 2021 | Not reported | 30 Jun 2023 | — | On date |
| Gami AstersP51700045247 | Navi Mumbai (M Corp.) | 2022 | Not reported | 31 Dec 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Gami Asters (P51700025311).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
