Terraferma Developers Llp

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Laxmi PrabhaP51800004266Andheri2017Certificate Signed30 Jun 201830 Jun 2018On date
Saujanya RachanaaP51800046295Andheri2022Certificate Signed31 Dec 202531 Dec 2025On date
Rachanaa AaravyaPR1180002502692Ambivali2026Certificate Signed30 Jun 202830 Oct 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Laxmi PrabhaOn date
  • Saujanya RachanaaOn date
  • Rachanaa Aaravya+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Rachanaa Aaravya (PR1180002502692).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology