Tejas Associates

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shri Gajanan TowerP50300003216Amravati (M Corp.)2017Completed30 Jul 201830 Jan 2021+30 months
Silver ParkP50300021853Amravati2019Certificate Signed28 Aug 202528 Aug 2025On date
Sai ParkP50300052820Amravati (M Corp.)2023Certificate Signed31 Dec 202731 Dec 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shri Gajanan Tower+30 mo
  • Silver ParkOn date
  • Sai ParkOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 30 months, for Shri Gajanan Tower (P50300003216).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology