Tater Realty
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
80%Kept RERA date4 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tater Florence Ivy-B WingP52000002578 | Karjat | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Tater Florence OliveP52000003313 | Karjat | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Tater Florence OrchidP52000003661 | Karjat | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Tater Florence Daisy-C WingP52000010005 | Karjat | 2017 | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Tater Florence TulipP52000021592 | Karjat | 2019 | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Tater Florence Ivy-B Wing (P52000002578).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology