Tarangan Infraventures Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+10 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pioneer TulipP50500000300Nagpur (M Corp.)2017Certificate Signed31 Mar 201931 Mar 2019On date
Pioneer Tamarind Court- Plot No.3P50500000429Nagpur (M Corp.)2017Certificate Signed31 Dec 201930 Oct 2020+10 months
Pioneer OrchidP50500017948Nagpur (M Corp.)2018Certificate Signed30 Jun 202331 Dec 2026+42 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pioneer TulipOn date
  • Pioneer Tamarind Court- Plot No.3+10 mo
  • Pioneer Orchid+42 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 42 months, for Pioneer Orchid (P50500017948).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology