Tabeer Properties
Company or firm · 4 projects · 4 MahaRERA registrations · 1 reported completed
4Projects4 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Arsh ResidencyP51600005289 | Nashik | 2017 | Certificate Signed | 31 Aug 2018 | 31 Aug 2018 | On date |
| Royal PalmP51600010474 | Nashik (M Corp.) | 2017 | Completed | 31 Dec 2018 | — | On date |
| Tabeer SpacesP51600023179 | Nashik (M Corp.) | 2019 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Tabeer VistaP51600055175 | Nashik (M Corp.) | 2024 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology