Skip to content
Deedo home
Menu

Swastik Realty Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+78 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Neelgagan CHS LtdP51800003974Andheri2017Not reported31 Dec 201830 Jun 2025+78 months
Vaibhav CHS LtdP51800004113Borivali2017Not reported30 Jun 201831 Dec 2025+90 months
Matruchaya CHS LtdP51800006910Andheri2017Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Neelgagan CHS Ltd+78 mo
  • Vaibhav CHS Ltd+90 mo
  • Matruchaya CHS LtdOn date

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 90 months, for Vaibhav CHS Ltd (P51800004113).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology