Swastik Estates

Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Yogmala Appartment Wing BP51600006719Jail Road2017Not reported31 Dec 201930 Dec 2021+24 months
Kalash Palace C WingP51600026544Jail Road2020Not reported30 Sep 2025—On date
Sai Kalash ApartmentP51600046015Jail Road2022Not reported31 Dec 2026—On date
Shubh Kalash ApartmentP51600050886Jail Road2023Not reported31 Dec 2029—On date
Amrut Kalash ApartmentPR1220002502640Jail Road2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Yogmala Appartment Wing B+24 mo
  • Kalash Palace C WingOn date
  • Sai Kalash ApartmentOn date
  • Shubh Kalash ApartmentOn date
  • Amrut Kalash ApartmentOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Yogmala Appartment Wing B (P51600006719).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology