Skip to content

Swaminarayan Life Space Llp

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 4 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Swaminarayan CityP51700018305Dombivli2018Certificate Signed30 Dec 202730 Apr 2028+4 months
Swaminarayan City Phase 1AP51700019326Dombivli2019Certificate Signed30 Dec 202930 Apr 2030+4 months
Swaminarayan City Phase 1BP51700031749Dombivli2021Certificate Signed31 Dec 202830 Apr 2029+4 months
Swaminarayan City Phase 1CP51700049570Dombivli2023Certificate Signed31 Dec 202930 Apr 2030+4 months
Swaminarayan City Phase 1DP51700055644Dombivli2024Active31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Swaminarayan City+4 mo
  • Swaminarayan City Phase 1A+4 mo
  • Swaminarayan City Phase 1B+4 mo
  • Swaminarayan City Phase 1C+4 mo
  • Swaminarayan City Phase 1DOn date

Track record notes

  • Longest extension on record: 4 months, for Swaminarayan City (P51700018305).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology