Suvasya Builders And Developers Llp

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Swastik PearlP51800024910Kurla2020Certificate Signed30 Dec 202430 Dec 2024On date
Swastik OnyxP51800034346Kurla2022Certificate Signed31 Dec 202531 Dec 2025On date
Swastik PlatinumP51800045216Kurla2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Swastik IrisP51800076792Bhandup2024Certificate Signed30 Jun 202930 Oct 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Swastik PearlOn date
  • Swastik OnyxOn date
  • Swastik Platinum+4 mo
  • Swastik Iris+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Swastik Platinum (P51800045216).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology