Skip to content

Sushant Gangurde

Individual promoter · 4 projects · 4 MahaRERA registrations

Also appears as Sushant Gangurde

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Samarth ShrushtiP51600018713Nashik2018Certificate Signed30 Mar 202330 Mar 2023On date
Samarth GloryP51600023373Chandshi2019Certificate Signed28 Nov 202328 Nov 2023On date
Samarth PrideP51600030350Chandshi2021Certificate Signed31 Dec 202231 Dec 2022On date
Jubiliant HeightsP51600033861Nashik (M Corp.)2022Certificate Signed31 Dec 202431 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Samarth ShrushtiOn date
  • Samarth GloryOn date
  • Samarth PrideOn date
  • Jubiliant HeightsOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology