Suryakant Kakade
Individual promoter · 5 projects · 5 MahaRERA registrations
Also appears as Suryakant Kakade
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kakade ParkP52100007904 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 25 Dec 2018 | — | On date |
| Kakade Plaza Phase 2 Jva MallP52100007918 | Kopare | 2017 | Not reported | 30 Dec 2019 | 30 Jun 2022 | +30 months |
| Kakade TownshipP52100011673 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 25 Mar 2019 | — | On date |
| Kakade Plaza Phase 1P52100012132 | Kopare | 2017 | Not reported | 30 Dec 2019 | — | On date |
| Sarvatra Co-Op Hsg Society LtdP52100051071 | Kothrud | 2023 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 30 months, for Kakade Plaza Phase 2 Jva Mall (P52100007918).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology