Skip to content
Deedo home
Menu

Surya Properties

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Lotus Laxmi 2P52100001075Haveli2017Certificate Signed30 Jun 201930 Jun 2019On date
Lotus Laxmi 3P52100015530Haveli2018Certificate Signed30 Sep 202030 Sep 2020On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Lotus Laxmi 2On date
  • Lotus Laxmi 3On date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology