Suratwwala Business Group Limited

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Suratwala Mark PlazzoP52100017784Mulshi2018Certificate Signed30 Dec 202230 Dec 2023+12 months
Suratwala Mark PlazzoP52100054055Mulshi2023Certificate Signed31 Dec 202930 Apr 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Suratwala Mark Plazzo+12 mo
  • Suratwala Mark Plazzo+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Suratwala Mark Plazzo (P52100017784).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology