SunVision Estates Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as SUN-VISION ESTATES LTD

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Swarup NiketanP51800001497Andheri2017Not reported28 Feb 201927 Feb 2020+12 months
Paresh KunjP51800001747Andheri2017Not reported30 Apr 201930 Jun 2022+38 months
Jai ShubamkarotiP51800002366Andheri2017Not reported31 Dec 2017—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Swarup Niketan+12 mo
  • Paresh Kunj+38 mo
  • Jai ShubamkarotiOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 38 months, for Paresh Kunj (P51800001747).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology