Sunrise Housing

Company or firm · 4 projects · 5 MahaRERA registrations

Projects45 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Parijatak Co Op Hsg Soc LtdP51800001974Kurla2017Not reported30 Dec 202030 Dec 2021+12 months
Mutual Benefit Co Op Hsg Soc LtdP51800002333Kurla2017Not reported31 Dec 2019—On date
Mulund Om CHS LtdP51800022406Kurla2019Not reported30 Dec 2024—On date
Isle Of CalmP51800077401Paspoli2024Not reported30 Mar 2029—On date
Isle Of CalmP51800077922Paspoli2024Not reported31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Parijatak Co Op Hsg Soc Ltd+12 mo
  • Mutual Benefit Co Op Hsg Soc LtdOn date
  • Mulund Om CHS LtdOn date
  • Isle Of CalmOn date
  • Isle Of CalmOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Parijatak Co Op Hsg Soc Ltd (P51800001974).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology