Skip to content

Sungrace Infra Projects

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anuraddha At 168/27P52100003277Manchar (Ct)2017Certificate Signed31 Dec 201831 Dec 2018On date
Project At S.no 168 H No 7/A/B/C/28b/30/8/29/3f/3yP52100007062Manchar (Ct)2017Certificate Signed30 Dec 202430 Dec 2024On date
Project At 168 19 Gulmohar ResidencyP52100023626Manchar (Ct)2019Certificate Signed30 Dec 202430 Dec 2024On date
Megh Malhar ResidencyP52100080196Manchar (Ct)2025Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anuraddha At 168/27On date
  • Project At S.no 168 H No 7/A/B/C/28b/30/8/29/3f/3yOn date
  • Project At 168 19 Gulmohar ResidencyOn date
  • Megh Malhar ResidencyOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology