Sumeru Realities
Company or firm · 5 projects · 5 MahaRERA registrations · 1 reported completed
5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sumeru residencyP51500009995 | Aurangabad (M Corp.) | 2017 | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Sumeru GreensP51500018343 | Aurangabad (M Corp.) | 2018 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Sumeru PrimeP51500023549 | Aurangabad (M Corp.) | 2019 | Certificate Signed | 13 Dec 2024 | 13 Dec 2024 | On date |
| Soham ResidencyP51500048162 | Aurangabad (M Corp.) | 2022 | Completed | 29 May 2025 | — | On date |
| Sumeru PearlsP51500077589 | Aurangabad (M Corp.) | 2024 | Active | 30 Jun 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology