Company or firm · 5 projects · 5 MahaRERA registrations · 1 reported completed

5Projects5 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sumeru residencyP51500009995Aurangabad (M Corp.)2017Certificate Signed31 Mar 201831 Mar 2018On date
Sumeru GreensP51500018343Aurangabad (M Corp.)2018Certificate Signed30 Dec 202230 Dec 2022On date
Sumeru PrimeP51500023549Aurangabad (M Corp.)2019Certificate Signed13 Dec 202413 Dec 2024On date
Soham ResidencyP51500048162Aurangabad (M Corp.)2022Completed29 May 2025—On date
Sumeru PearlsP51500077589Aurangabad (M Corp.)2024Active30 Jun 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sumeru residencyOn date
  • Sumeru GreensOn date
  • Sumeru PrimeOn date
  • Soham ResidencyOn date
  • Sumeru PearlsOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology