Sukhwani Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+20 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sukhwani AmbarP52100026576Mulshi2020Not reported30 Jun 2027—On date
Sukhwani Niketan Phase IIP52100029575Pimpri Chinchawad (M Corp.)2021Not reported30 Nov 202331 Mar 2027+40 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sukhwani AmbarOn date
  • Sukhwani Niketan Phase II+40 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 40 months, for Sukhwani Niketan Phase II (P52100029575).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology