Sukhmani Constructions
Company or firm · 7 projects · 7 MahaRERA registrations
Projects77 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Gobind RegencyP52100005810 | Mahalunge | 2017 | Not reported | 28 Nov 2023 | — | On date |
| Gobind PlazaP52900010881 | Sawantwadi (M Cl) | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Gobind SamarthP52900013448 | Sawantwadi (M Cl) | 2017 | Not reported | 10 Mar 2023 | — | On date |
| Gobind KripaP52900021099 | Sawantwadi (M Cl) | 2019 | Not reported | 30 Dec 2024 | — | On date |
| Gobind DhamP52900046685 | Sawantwadi (M Cl) | 2022 | Not reported | 31 Dec 2027 | — | On date |
| Gobind ComplexP52900049333 | Sawantwadi | 2023 | Not reported | 31 Mar 2028 | — | On date |
| Gobind DarshanP52900055093 | Sawantwadi (M Cl) | 2024 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
Regulatory cases across projects
- DeregisteredDeregistered: GOBIND DHAM · Gobind Dham · P52900046685
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology