Sugee Six Developers Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
PrekshaP51900000978Ward Fnorth2017Not reported30 Sep 202030 Mar 2022+18 months
Sugee SamruddhiP51900056033Ward Gnorth2024Not reported31 Aug 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Preksha+18 mo
  • Sugee SamruddhiOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Preksha (P51900000978).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology