Company or firm · 1 project · 1 MahaRERA registration

Also appears as Sudhir Gulati

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shiv AnshP52000047973Kharghar2022Certificate Signed30 Nov 202930 Mar 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shiv Ansh+4 mo

Track record notes

  • Longest extension on record: 4 months, for Shiv Ansh (P52000047973).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology