Sudhir Ashok Mandale

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
California HeightsP52100005103Rakshewadi2017Certificate Signed31 Dec 201931 Dec 2019On date
Krishnakala co-operative Housing society LimitedPM1260002501124Pune (M Corp.)2025Certificate Signed1 Jun 20281 Oct 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • California HeightsOn date
  • Krishnakala co-operative Housing society Limited+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Krishnakala co-operative Housing society Limited (PM1260002501124).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology