Sudhanshu Infrastructures Pvt Ltd
Company or firm · 7 projects · 7 MahaRERA registrations
Also appears as SUDHANSHU INFRASTRUCTURES PRIVATE LIMITED · Shudhanshu Infrastructures Pvt Ltd
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 5 extended
3Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sudhanshu ImperiaP51800003303 | Kurla | 2017 | Certificate Signed | 1 Feb 2020 | 30 Dec 2021 | +22 months |
| Vishnu Bhaskar Chs LtdP51800015748 | Kurla | 2018 | Certificate Signed | 10 Sep 2019 | 26 Mar 2024 | +54 months |
| Sudhanshu HeightsP51800019314 | Kurla | 2019 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Aniraj Tower Chs LtdP51800024276 | Kurla | 2020 | Active | 30 Dec 2025 | — | On date |
| Sudhanshu Imperia Wing CP51800027547 | Kurla | 2020 | Certificate Signed | 30 Jun 2023 | 31 Mar 2026 | +33 months |
| Bhandup Amol Chs LtdP51800050455 | Bhandup | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Paul ChamberPR1180002501359 | Kanjurmarg | 2025 | Certificate Signed | 12 Aug 2027 | 12 Dec 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 54 months, for Vishnu Bhaskar Chs Ltd (P51800015748).
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- complaintComplaint CC12400377 · Aniraj Tower Chs Ltd · P51800024276
- complaintComplaint CC12502874 · Aniraj Tower Chs Ltd · P51800024276
- complaintComplaint CC12502875 · Aniraj Tower Chs Ltd · P51800024276
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology