Sudarsan Homes Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sudarsan Jai Ghanshyam KrupaP51800052062Vileparle2023Certificate Signed1 Sep 20251 Sep 2025On date
Sudarsan SatyanivasPR1180002600894Kondivita2026Certificate Signed28 Nov 202828 Mar 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sudarsan Jai Ghanshyam KrupaOn date
  • Sudarsan Satyanivas+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Sudarsan Satyanivas (PR1180002600894).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology