Starwing Developers Private Limited
Company or firm · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Apurva ResidenciesP51800000167 | Andheri | 2017 | Not reported | 30 Jun 2018 | — | On date |
| Kaatyayni Heights Phase 1P51800011980 | Andheri | 2017 | Not reported | 30 Jun 2023 | — | On date |
| Kaatyayni EnclaveP51800012277 | Andheri | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Kaatyayni Heights Tower 2 Phase 2P51800020411 | Andheri | 2019 | Not reported | 30 Dec 2024 | 30 Jun 2025 | +6 months |
| Stellar HeightsP51800049642 | Marol | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Dhan NarainPR1180002501305 | Bandra | 2025 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 6 months, for Kaatyayni Heights Tower 2 Phase 2 (P51800020411).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology