2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+46 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Usha Kiran Residency F1 F2P51700004142Badlapur (M Cl)2017Certificate Signed31 Dec 201831 Jul 2026+91 months
Usha Kiran Residency Wing E1 E2 E3P51700012135Badlapur (M Cl)2017Certificate Signed31 Dec 201731 Dec 2017On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Usha Kiran Residency F1 F2+91 mo
  • Usha Kiran Residency Wing E1 E2 E3On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 91 months, for Usha Kiran Residency F1 F2 (P51700004142).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology