Spl Construction

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai-Krupa ComplexP52800051460Pachal2023Certificate Signed30 Nov 203130 Mar 2032+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai-Krupa Complex+4 mo

Track record notes

  • Longest extension on record: 4 months, for Sai-Krupa Complex (P52800051460).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology