Spenta Enclave Private Limited

Company or firm · 3 projects · 6 MahaRERA registrations

3Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+30 moMedian delayvs RERA proposed date · 5 extended
6Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AltavistaP51800000956Kurla2017Certificate Signed30 Jun 202830 Oct 2028+4 months
AltavistaP51800001050Kurla2017Certificate Signed31 Dec 201931 Jul 2024+55 months
AltavistaP51800021249Kurla2019Not reported30 Jun 2028—On date
AltavistaP51800026131Kurla2020Certificate Signed30 Dec 202431 Dec 2029+60 months
Ornata - SapphireP51800026905Kurla2020Certificate Signed30 Jun 202830 Oct 2028+4 months
Ornata - AmberP51800028964Kurla2021Not reported31 Dec 202431 Dec 2029+60 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Altavista+4 mo
  • Altavista+55 mo
  • AltavistaOn date
  • Altavista+60 mo
  • Ornata - Sapphire+4 mo
  • Ornata - Amber+60 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 60 months, for Altavista (P51800026131).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology