Sohanlal Realty Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mahalaxmi Nagar 25 Sector - 2P50500046511Jamtha2022Certificate Signed8 Jul 20268 Jul 2026On date
Mahalaxmi Nagar 25 Sector 3P50500047957Jamtha2022Certificate Signed20 Oct 202820 Oct 2028On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mahalaxmi Nagar 25 Sector - 2On date
  • Mahalaxmi Nagar 25 Sector 3On date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology