Sobha Limited
Company or firm · 1 project · 3 MahaRERA registrations
1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sobha NesaraP52100020034 | Kothrud | 2019 | Certificate Signed | 30 Mar 2025 | 30 Sep 2025 | +6 months |
| Sobha NesaraP52100020057 | Kothrud | 2019 | Certificate Signed | 30 Mar 2025 | 30 Mar 2026 | +12 months |
| Sobha NesaraP52100020062 | Kothrud | 2019 | Certificate Signed | 30 Mar 2025 | 31 Mar 2027 | +24 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Sobha Nesara (P52100020062).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology