Sobha Limited

Company or firm · 1 project · 3 MahaRERA registrations

1Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sobha NesaraP52100020034Kothrud2019Certificate Signed30 Mar 202530 Sep 2025+6 months
Sobha NesaraP52100020057Kothrud2019Certificate Signed30 Mar 202530 Mar 2026+12 months
Sobha NesaraP52100020062Kothrud2019Certificate Signed30 Mar 202531 Mar 2027+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sobha Nesara+6 mo
  • Sobha Nesara+12 mo
  • Sobha Nesara+24 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Sobha Nesara (P52100020062).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology