Soba Associates

Company or firm · 2 projects · 3 MahaRERA registrations

Also appears as M/S. SOBA ASSOCIATES

Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SaffronP52100013262Kothrud2017Not reported20 Dec 2020—On date
SaffronP52100016249Kothrud2018Not reported20 Dec 2020—On date
Optima 2.0P52100018793Wadgaon Bk2018Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • SaffronOn date
  • SaffronOn date
  • Optima 2.0On date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.