Sneha Construction
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as SNEHA CONSTRUCTIONS
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Riddhi Siddhi EnclaveP52100004206 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Kohinoor BP52100079574 | Haveli | 2025 | Certificate Signed | 28 Feb 2029 | 28 Jun 2029 | +4 months |
| Kohinoor A/CP52100079612 | Haveli | 2025 | Certificate Signed | 28 Feb 2029 | 28 Jun 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Kohinoor B (P52100079574).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology