Skyline Construction Co

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as SKYLINE CONSTRUCTION CO.

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Building on Sub plot - D, CTS No 101/B of village GoregaonP51800007873Borivali2017Certificate Signed31 Oct 201930 Oct 2021+24 months
Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali WestP51800008028Borivali2017Certificate Signed31 Dec 201931 Dec 2019On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Building on Sub plot - D, CTS No 101/B of village Goregaon+24 mo
  • Building on Sub Plot A CTS No 283 D pt 287 A pt 287 B 1 and 616 A at Kandivali WestOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Building on Sub plot - D, CTS No 101/B of village Goregaon (P51800007873).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology