Siroyafm Constructions Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
OrchidP51800004021Andheri2017Not reported20 Oct 2019—On date
New JagdambaP51800008985Andheri2017Not reported30 Nov 2026—On date
KalaniketanP51800009790Kurla2017Certificate Signed31 Jan 201831 Jan 2019+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • OrchidOn date
  • New JagdambaOn date
  • Kalaniketan+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Kalaniketan (P51800009790).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology